Once you’ve added all your rooms to the site floor plan, you can start to add hardware. There's a particular order in which to do this:

1. Add Hubs

  1. Begin by dragging an AI Security Hub to where it will be installed on the floor plan

<aside> 💡

If hardware is yet to arrive or be allocated, you can set the serial number as unassigned and update it later

</aside>

2. Add doors

  1. Drag a door to the wall it is positioned on. This will connect rooms together, and external walls to Outside. When you first add a door, it will appear as being disconnected
  2. Click on a disconnected door and select Link with Hub to start setup
  3. Select the Hub and channel this door will be connected to
  4. Select which side of the wall the reader is on, whether a REX is fitted, if there is a door status input, and whether there are EOL resistors installed